By Nawaz Sayyed
In
an exclusive talk with Mr. Ajit Kumar Jain Managing Director of Mishal
Construction Group, he has shared his experience with us on society
redevelopment.
- What is need of redevelopment of housing societies and what is the benefit to the members of the housing society.
Redevelopment
is generally described as newborn construction on an old plot which has
pre existing structure in any housing society. It gives an opportunity
to refurbish old residential complexes keeping pace with changing life
styles and facilities to upgrade the standard of people who are living
in old structures and also creates space for new people. Redevelopment
is an hot issue today as vacant and un-encroached land Is hardly
available in Mumbai city to carry out the further development of the
residential/commercial properties. Today in Mumbai city many
co-operative societies are in need of structural repairs as the
structure of the societies is more than 40 years old and life of the
said structure is expires and also society find it difficult to arrange
the funds require to carry out the same. The growth in size of families
and in the need of larger accommodations. The old housing societies are
have other drawbacks also such as lack of securities, non availability
of the play areas for children’s, lack of parking space, pertinent
leakage problems, absence of elevators in the building which is a major
drawback in societies specially for the old age citizens, resale value
of flat due to poor condition of the existing buildings and unprivileged
planning of rooms and many more. There are various advantages for those
societies who opt for redevelopment of their existing properties in to
new structure having grand entrance lobby, spacious staircase and lobby,
modern elevators, adequate parking space as per norms, exclusive
society office, gymnasium, health club, a 24 hours security, stand by
generators for essential services, efficient fire fighting systems,
under ground and over head tanks with submersible pumps, provisions for
pipe gas connections etc.. For the existing members they will benefited
with additional carpet area in the new building, the additional area and
other benefits is depend upon the locality and the utilization of the
FSI on said plot. Apart from the additional carpet area if any members
wants additional carpet area over above their entitlement in the same
building it can be achieved by purchasing from the developer at the
negotiated cost as per the mutual agreed terms. This would enable
families to live in the same locality, enjoying life with more luxury
with an ultra modern amenities. On the other hand A major financial
benefit of corpus funds to the society/member which take care of the
revised maintenance cost in the new premises and rent for temporary
accommodations till the possession is handed over in the newly
constructed buildings. Redevelopment has made a very positive approach
that has transformed many housing societies in metro cities in to a land
mark complexes and towers.
- If a housing soc. Wants to redevelop their soc. Then what is the procedure for redevelopment?
Redevelopment
of housing societies is usually burdened with bitterness and complaints
of high-handedness against the Managing Committee. Hence, with a view
to ensure transparency in societies seeking to undertake redevelopment
projects, the state co-operative department has, for the first time,
issued guidelines for societies to follow under section 79 (A) of the
Maharashtra Co-operatives act, 1960.
The
special general body has to approve the bid of the successful bidder in
a meeting attended by the registrar. The entire proceedings have to be
video-recorded.
Stages of Redevelopment
Offer letter to the society:
The Housing Society is required to inviting the tenders from the
Developers and a Redevelopment Committee is formed to shortlist
Developers on merits and the comparative data is placed before the SPGM
for final selection. The selected Developer is informed accordingly and
his terms are invited in writing as an Offer letter to the society.
Terms and conditions with the society:
The first step towards the re-development is agreeing on the
basic terms and conditions between the members and the Developer. The
broad terms and conditions will include extra area, corpus money,
shifting charges, alternate accommodation, time of re-development,
amenities in the new building, etc.
Finalizing the plans with members:
After due consultation with all the members, the plan will be made to
suit the requirements of the existing members and will be approved by
them before applying for sanction from MCGM
Agreement with the society:
The execution of the development agreement will be done once the above
two points have been cleared by both the parties and after the
draft copy of the agreement have been approved by the solicitors of both
the parties. It is possible to appoint a common solicitor so as to
reduce the time in execution of the document
Sanction from MCGM in favour of the society:
After the execution of the development agreement, plans are put up for
sanction from MCGM with regards to the entire layout as well as the
concession plans in favour of TWO FSI. This step makes the society feel
safe and confident towards the Developer.
Obtaining the IOD:
After concession approval is done by the municipal commissioner the IOD
is obtained from the MCGM, the Developer then starts fulfilling all the
conditions as mentioned in the IOD before obtaining the Commence
Certificate.
Shifting of the members:
The members will feel lot more confident after the IOD is been obtained
from the MCGM. The members will now shift into their alternate
accommodation as a pre-requisite before demolition of the building which
is a must before obtaining the CC from MCGM
Demolition of the building:
Once the members have shifted into their alternate accommodation, the
demolition of the building will take place either all the wings
simultaneously or phase wise depending upon the scheme of
re-development. Usually about two months are given to the members from
the date of obtaining IOD before asking them to shift to the alternate
accommodation
Obtaining the CC:
The IOD approval and demolition of the building will be followed by the
issue of the CC (plinth level) by the MCGM which shall enable the
Developer to start the construction work and after the plinth lines are
verified by the MCGM officers, the further CC is granted for the
complete building.
Construction of the building:
The building construction work will began in full earnest as per the
approved plans by the MCGM taking into consideration the various safety
factors to be considered during the construction work. The quality and
the amenities will be provided as per agreed terms and conditions.
Obtaining the OC:
The last step before the construction work is termed as complete is
obtaining the Occupation Certificate enabling the Developer to allot the
occupation to the old as well as the new member
Shifting the old members:
On receipt of the Occupancy Certificate the Developer can lawfully
allow the possession of the flats to be taken over by their owners
- Recently BMC has imposed “New Capital Value based Property tax System” What you think is it in favour of property owner?
The
new capital value-based property tax system that comes into effect from
April 2010 will impact more than two lakh self-occupied, leased and
vacant properties in the city. The civic authority has extended the
deadline for paying the taxes to June 30, following 35,000-odd
complaints. The new system will increase tax by 100-300%, hurt the
city's redevelopment market and even force many to move outside the
city. The Property Owners' Association is now considering an option to
move the court against the capital value-based property tax system. The
association, which represents 2,700 property owners controlling
more than 10,000 buildings in Mumbai, has been organizing joint
meetings and seminars to alert members and marshal public
support. According to the BMC proposal, property tax on residences will
be calculated at 0.41% of its capital value. For offices, the tax will
be at 1.95% of the capital value, and for banks, it's at 3.91%. The new
tax will be calculated on the basis of the current market value or
capital value of the property based on factors, like age, price,
location, and type of property.
4.The
MISHAL group is also concentrating in redevelopment segment, so now a
day’s how many projects are under process and how many redevelopment
projects group has done till date?
We
are in construction industries since last 10 years especially into
redevelopment of old properties and housing societies and to our credit
we have delivered quality, Vastu compatible state of art landmark
projects of various magnitudes across the city in Mumbai and also have a
huge nos. of redevelopment project in hand under the various stages.
Our dedicated team comprises of hard working dedicated people & thus
we have successfully created and earned an excellent reputation in the
field. Of the various major factors that has helped us create this
unique position in the highly competitive housing sector, on time
delivery, commitment fulfillment, positive attitude, quality &
transparency has been our benchmark.
- What is your view on RBI’s move for reduction in the repo rate by 25 basis points?
''The
RBI's decision to reduce the repo rate by 25 bps from 7.75 to 7.5% is
good news for real estate industry. This is definitely going to provide
some respite to the real estate industry. The reduction in the repo
rate will definitely affect the consumers positively as reduction
in repo rate will improve the liquidity in the market at some extent and
will reduce the interest burden in the coming days.